Generator Wattage Chart - Running and Starting Watts for Common Loads

Generator sizing runs on two numbers per load: the watts it draws once running, and the watts it demands for the first seconds of starting. This chart gives typical figures for the loads that decide home backup size, and shows how the starting column, not the running column, picks the generator.

Built to NEC 2023 tables. No reviewer claim until a licensed reviewer is signed.

The chart

Figures are typical planning values for each load class, the same basis this site's sizing tools use. Any single appliance can sit outside its row: the nameplate, and better still a plug-in power meter, outrank the chart for your own equipment.

LoadRunning watts (typical)Starting watts (typical)
Refrigerator100 to 200300 to 1,000
Well pump, 1/2 HPAbout 750About 3,750
Furnace blower500 to 9001,500 to 2,700
Central AC, 3 tonAbout 3,50010,500 to 17,500
Sump pump, 1/3 HP600 to 9001,800 to 2,700
Microwave, 1,200 W cooking ratingAbout 1,700 inputSame as running
Electric water heater, 4,500 W4,500Same as running

Read the chart by load type. Anything with a motor that starts across the line, the fridge compressor, the pumps, the blower, the AC, carries a starting figure several times its running figure, because a stationary motor is nearly a short circuit until it spins up. Resistive loads, the water heater, and inverter-driven loads like the microwave draw the same watts in the first second as in the hundredth hour. The microwave row carries a second lesson: its cooking rating is output, and the input it draws from the supply, about 1,700 W for a 1,200 W rating, is the figure a generator feels.

Why starting watts decide the size

A generator does not experience your loads as a tidy sum. It experiences a running total, and then, without warning, a motor start on top of it. The engine and alternator have to hold voltage and frequency through that surge or everything connected stumbles: electronics reset, the AC compressor may stall and draw locked-rotor current far longer, and the generator's own protection can end the experiment. That is why the sizing question is never just "how many running watts" but "what is the largest single start, and what else is running when it happens".

Worked from the chart's top-of-range figures: a house carrying the fridge at 200 W and the furnace blower at 900 W is running 1,100 W, a trivial load. The well pump starts: add its 3,750 W surge and the generator must deliver about 4,850 W in that moment. A set bought as "5,000 W" on its running rating is at its ceiling with no reserve for the next start or the sump pump joining in; the comfortable answer is the next size class up. The generator size calculator formalises exactly this: running total, demand allowance, largest motor surge, reserve, and the standard set size the combination lands on.

Reading a load list into the sizing tool

The method the chart feeds is short. List what must run during an outage, not what would be nice. Take the running watts of everything that can run at once, using the chart or your nameplates. Find the largest starting figure among the motor loads and add the surge portion, the starting watts above that motor's own running watts, to the running total; two large motors rarely start in the same second, so one surge allowance is the honest planning figure. Add reserve, a fifth to a quarter, for the load you forgot and for the set ageing. Resistive giants deserve a decision rather than a default: an electric water heater or range on the backup list can double the generator for the sake of loads that tolerate waiting until the power returns, and many whole-house plans deliberately leave them off. Soft starters change the AC row specifically, cutting a compressor's starting demand sharply, and are the standard answer when a modest set must start a large air conditioner.

The AC nameplate gives a better starting figure

The chart's AC row is a range because air conditioners vary, but your own unit removes the guesswork: its nameplate states the compressor's locked-rotor amps, marked LRA. Multiply the LRA by the unit's voltage and the result is the starting VA the generator must survive, in volt-amps rather than watts, which for a stumbling generator is the honest unit anyway. A unit marked 75 LRA at 240 V presents about 18,000 VA of starting demand, at the top of the chart's range, while a soft starter fitted to the same unit can cut that figure by half or more, which is why the soft starter decision belongs in the sizing conversation and not after it. The running side of the same plate, the rated-load amps, does the same service for the running column. Two minutes with the nameplate converts this chart from typical to specific for the single load that dominates most whole-house decisions.

Worked with the AC in the picture: fridge at 200 W and lights and network gear at a few hundred more, call the running total 500 W with the AC running at 3,500 W on top, so about 4,000 W steady. The AC cycles off and restarts against that base: at the chart's top starting figure the momentary demand reaches roughly 18,000 VA, which no 10 kW class set holds gracefully, and which a soft starter brings back inside the range a set of that class handles as routine. This is the commonest whole-house outcome the chart produces: either the generator grows to the AC's surge, or the AC's surge shrinks to the generator, and pretending neither is necessary is how undersized sets get bought.

Fuel follows size

The size this chart argues for is also the size that drinks the fuel. A larger set burns more per hour at the same delivered load, because part-load efficiency falls as the set grows relative to its work. Sizing honestly, rather than generously, is therefore a fuel decision as much as a purchase decision: the generator fuel consumption calculator turns the chosen size and your expected load level into burn per hour, per day and per tank, which is the number that decides how much fuel the plan has to store.

Planning only

This guide is a planning reference built on NEC 2023 methods, with load figures stated as typical planning values. Your equipment nameplates and meter readings govern your own list, and generator installation, transfer equipment and permitting belong with your authority having jurisdiction and your licensed electrician.